Is there any need of running Adjust Cost for Serialized Items ? :-k My costing method is specific. As for some items in item ledger entry table i have Applied Entry to Adjust checked even for the ones which are not open anymore. My database version is 5.0 not SP1.
0
Comments
-
Yes you need to run adjust cost.0
-
Reason :?: As we know that if costing method is serialized then what come in exactly goes out at the same cost. I have an issue in which there is cost difference but no Item Charges or Revaluation has been done. That is why i wondered that i am correct in thinking or not.
Can you explain me when and how this can happen :?:0 -
asking wrote:
Can you explain me when and how this can happen :?:
Consider this example whether you use serial or not
U created a Purchase order on 02/02/02 qty = 10 Unit cost = 10 Total value = 100
Receipt : 09/02/02 receive the material , then system updates Total value in Cost amount (Expected) / serial No = Abc001 in item ledger entry
U created the sales order on 15/02/02 qty = 10 Unit cost = 20 Total value = 200
Ship & Invoice : qty = 10 , serial No = Abc 001. on 15/02/02.
Then system update the Item ledger entries with these values :
Entry Type = sale
Cost amount (Actaul) = -100 ,
sales amount ( actual) = 200.
But u created the Purchase invoice on against that serial Number ABC001. With unit cost = 15 , total amount = 150.on 18/02/02.
So Now when u run the AICE batch Job then system adjust the cost to that sale entry.
Entry Type = sale
Cost amount (Actaul) = -150 ,
sales amount ( actual) = 200.0 -
To sum that up:
You can receive an item and sell it before you've invoiced the purchase. The cost may have changed during that time so adjust cost must be run.
I asked the same thing not too long ago and what finally made it click for me was what, I think David Singleton said: Specific costing is just FIFO limited to one item.0 -
asking wrote:Is there any need of running Adjust Cost for Serialized Items ? :-k My costing method is specific. As for some items in item ledger entry table i have Applied Entry to Adjust checked even for the ones which are not open anymore. My database version is 5.0 not SP1.
An Addition: If u have "Never" selected as an option in "Automatic Cost Adjustment" then it will be checked by the time you do not Adjust Cost.. .Kapil Khanna0 -
kapil4dynamics wrote:An Addition: If u have "Never" selected as an option in "Automatic Cost Adjustment" then it will be checked by the time you do not Adjust Cost.. .
Hi Kapil,
Can i know what is this statement meaning ?
can u elaborate ?
Thanksameen0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.6K Microsoft Dynamics NAV
- 18.7K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 320 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions