Released Prod.Order Duedate

mohana_cse06
Member Posts: 5,506
Hi All
I am creating a new Released Prod.Order with duedate=Workdate (Workdate = 01/27/11)
if i do refresh dere is no change in due date.
if i give duedate 02/06/11.(W+10D) and refresh den duedate is changed to 02/05/11.
Can u plz tell me y its happening?
](*,)
I am creating a new Released Prod.Order with duedate=Workdate (Workdate = 01/27/11)
if i do refresh dere is no change in due date.
if i give duedate 02/06/11.(W+10D) and refresh den duedate is changed to 02/05/11.
Can u plz tell me y its happening?
](*,)
0
Comments
-
The reason for this is that 02/06/11 is not a working day (it is weekend). When you do a refresh NAV will schedule all your capacity need (work centers and machine centers) so it happens within the calendar you have defined for each work / machine center. So in order to finish production before before 02/06/11 NAV will need to have the last operation finished on Friday 02/04/11.
Because you have a "Default Safety Lead Time" = 1D (is set on Manufacturing Setup form) NAV adds 1 day to the day of the last operation and thus the due date becomes 02/05/11.Jens Tidemann
Microsoft, Dynamics NAV
This posting is provided "AS IS" with no warranties, and confers no rights.0 -
thanks alot.. =D>
so it happends only on sundays..0 -
I got one more doubt..
Sat day is also holiday..but we are getting same due date.
Why? :^o0 -
That is becauce the "Default Safety Lead Time" is set to 1D (you can change that on Manufacturing Setup form (found in Navigation Pane under Manufacturing -> Setup)). NAV will first calculate when your production order is complete (Friday) then it will add the "Default Safety Lead Time" (+1 day = Saturday) and make that the due date.
At first glance it might seem strange that the "Default Safety Lead Time" does not respect the calendar, but the calendar is defined for each Work / Machine Center individually, so it cannot use those calendars in the calculation.Jens Tidemann
Microsoft, Dynamics NAV
This posting is provided "AS IS" with no warranties, and confers no rights.0 -
Jens Tidemann wrote:That is becauce the "Default Safety Lead Time" is set to 1D (you can change that on Manufacturing Setup form (found in Navigation Pane under Manufacturing -> Setup)). NAV will first calculate when your production order is complete (Friday) then it will add the "Default Safety Lead Time" (+1 day = Saturday) and make that the due date.
At first glance it might seem strange that the "Default Safety Lead Time" does not respect the calendar, but the calendar is defined for each Work / Machine Center individually, so it cannot use those calendars in the calculation.
Confusion #-o
But I vl try to Understand :oops:
Thanks
once again0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.6K Microsoft Dynamics NAV
- 18.7K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 320 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions