Strange Starting & Ending DateTime in Firm Plan. Prod. Order
amphysvena
Member Posts: 113
Hi,
I want to ask about starting & ending date time in Firm Planned Prod. Order.
In Cronus database (NAV 4 SP3):
- create a new Work Center. Unit of measure code:HOURS. Shop calendar using 3 shifts.
Every shifts is 8 hours. Start from Monday: 8 AM until Sunday 8 AM.
- create new routing, type Serial. Using the new created work center, with lot size = 2800, run time = 24
- Set item A routing no. using the new created routing.
- create a new firm planned prod. order, source type = item, source no. = A, quantity 2800.
- Function refresh, which create new line :
Item = A, Quantity = 2800, Starting Date Time : 01/23/01 11:00:13 PM
Ending Date Time : 01/24/01 11:00:00 PM
The workdate is 25 January 2001.
I'm expecting, the difference between Starting & Ending date time will be exactly 24 hours. But it is not. Could somebody help me, explaining where does the date time comes from? & Why it doesn't 24 hours?
Thanks. Sorry for my bad English
Regards,
Alphonse
I want to ask about starting & ending date time in Firm Planned Prod. Order.
In Cronus database (NAV 4 SP3):
- create a new Work Center. Unit of measure code:HOURS. Shop calendar using 3 shifts.
Every shifts is 8 hours. Start from Monday: 8 AM until Sunday 8 AM.
- create new routing, type Serial. Using the new created work center, with lot size = 2800, run time = 24
- Set item A routing no. using the new created routing.
- create a new firm planned prod. order, source type = item, source no. = A, quantity 2800.
- Function refresh, which create new line :
Item = A, Quantity = 2800, Starting Date Time : 01/23/01 11:00:13 PM
Ending Date Time : 01/24/01 11:00:00 PM
The workdate is 25 January 2001.
I'm expecting, the difference between Starting & Ending date time will be exactly 24 hours. But it is not. Could somebody help me, explaining where does the date time comes from? & Why it doesn't 24 hours?
Thanks. Sorry for my bad English
Regards,
Alphonse
0
Comments
-
Hi Alphonse,
Do you have a set-up time or wait time specified?0 -
Hi Dave,
No, I don't specify any wait time & setup time. Its zero in routing line.
Thanks0 -
In routing Line keep changing the , setup time,run time and Move time . Refresh the Firm Planned order.
U can know the difference how it is calculating the dates.reema0 -
Hi Reema,
Sorry if i misunderstand you. But I only want to use run time. While other (Move Time, Setup time, Wait time) is zero.
Thanks0 -
What I means to say if u are not filling these fields then try to change the value in run time .
Check the dates how those are changing based on the run time.reema0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.7K Microsoft Dynamics NAV
- 18.8K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 328 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions