Hi,
I want to ask about starting & ending date time in Firm Planned Prod. Order.
In Cronus database (NAV 4 SP3):
- create a new Work Center. Unit of measure code:HOURS. Shop calendar using 3 shifts.
Every shifts is 8 hours. Start from Monday: 8 AM until Sunday 8 AM.
- create new routing, type Serial. Using the new created work center, with lot size = 2800, run time = 24
- Set item A routing no. using the new created routing.
- create a new firm planned prod. order, source type = item, source no. = A, quantity 2800.
- Function refresh, which create new line :
Item = A, Quantity = 2800, Starting Date Time : 01/23/01 11:00:13 PM
Ending Date Time : 01/24/01 11:00:00 PM
The workdate is 25 January 2001.
I'm expecting, the difference between Starting & Ending date time will be exactly 24 hours. But it is not. Could somebody help me, explaining where does the date time comes from? & Why it doesn't 24 hours?
Thanks. Sorry for my bad English
Regards,
Alphonse
0
Comments
Do you have a set-up time or wait time specified?
Dynamics Nav Add-ons
http://www.simplydynamics.ie/Addons.html
No, I don't specify any wait time & setup time. Its zero in routing line.
Thanks
U can know the difference how it is calculating the dates.
Sorry if i misunderstand you. But I only want to use run time. While other (Move Time, Setup time, Wait time) is zero.
Thanks
Check the dates how those are changing based on the run time.