Hi, we have items with uncorrect Costing method.
We would like to change the costing method, but navision hinders us to do so,
because of entries in Item ledgery Entry.

it is a simple security programming in the validation of the "costing method"
in table 27 "Item"

we would like to outcomment this security programming, change the costing method and then activate the programming.

Are there anybody how has this done before?
Or what else can we do?
(create a new item is impossible)

Comments

  • kinekine Member Posts: 12,562
    Yes, please, do not skip this check. It has meaning. Do it as BlackTiger wrote. Else you will have problems with costing on this item and it is not so easy to correct it...
    Kamil Sacek
    MVP - Dynamics NAV