Project/Resource Planning
So here is the problem I'm having (BC cloud, version 27.3):
I have a project planning line with a single resource on it, and that resource is only available for 40 hours a week.
If I enter a task that requires 160+ hours, the system doesn't seem smart enough to change the dates accordingly.
This is confusing to me for several reasons:
1. What is the point of having resource availability in the system if they can just be overloaded without so much as a warning message?
2. The only way I can think to get around this is to enter a single line for each week, or god forbid, day. There doesn't appear to be a function to even assist with this.
I feel like I'm missing something critical here, because this type of functionality seems really, really basic for any kind of project management tool, so I'm very much hoping that it exists and I just haven't figured it out yet.
Any pointers would be greatly appreciated.
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.7K Microsoft Dynamics NAV
- 18.8K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 333 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 991 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions