I need to upgrade 2 reports from v5 Nav to 2013 R2. Every link I see online for a tool has now expired. Does anyone have a tool or advice on how to complete this task? Both reports are processing only.
Hello,
you do not need any conversion tool to migrate "processing only" reports.
You can manually create a new report in NAV2013 R2 with the same DataItems and copy your code from NAV5 to the new report in NAV2013 R2.
From the request form in NAV5 you manually create a new request page in NAV2013.
Answers
you do not need any conversion tool to migrate "processing only" reports.
You can manually create a new report in NAV2013 R2 with the same DataItems and copy your code from NAV5 to the new report in NAV2013 R2.
From the request form in NAV5 you manually create a new request page in NAV2013.