Hi,
I'm aware that the start time and end time are related by the routing time. However, we are wanting to override the Start Time that is derived from the backward scheduling.
However, any change we make to the Start Time always updates the end time, by the amount of the routing time. Is there any way to bypass this, so we can manually override start/end times on a production order? We are working with Released Production Orders only.