Hello Guys!
I am setting parameter to NAV3.6 and trying to launch MPS/MRP regenerative scheduling.
I have an item to sell, with inv=0, lead time=40g.
System requests a purchase order, and lead time calculation (finish-start) equals exacltly to lead time (40G), but:
- the interval is calculated in calendar days (not working days!)
- the start date of po occurs on Sunday (calendar in GL is set up correctly)
Could you help me before to contact my NSC?
Thanks a lot!
Paolo