Lead time Calculation

paolo_689
Member Posts: 2
Hello Guys!
I am setting parameter to NAV3.6 and trying to launch MPS/MRP regenerative scheduling.
I have an item to sell, with inv=0, lead time=40g.
System requests a purchase order, and lead time calculation (finish-start) equals exacltly to lead time (40G), but:
- the interval is calculated in calendar days (not working days!)
- the start date of po occurs on Sunday (calendar in GL is set up correctly)
Could you help me before to contact my NSC?
Thanks a lot!
Paolo
I am setting parameter to NAV3.6 and trying to launch MPS/MRP regenerative scheduling.
I have an item to sell, with inv=0, lead time=40g.
System requests a purchase order, and lead time calculation (finish-start) equals exacltly to lead time (40G), but:
- the interval is calculated in calendar days (not working days!)
- the start date of po occurs on Sunday (calendar in GL is set up correctly)
Could you help me before to contact my NSC?
Thanks a lot!
Paolo
0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.6K Microsoft Dynamics NAV
- 18.7K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 320 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions