I'am upgrading an NAV 70 database to NAV 110. To make the porocess easier, I would like to start the process "Transfer Data" via c/al code for each company. The database have ~30 companies. I start the clients with 'Windows Script Host Object Model'.WshShell" automation variable and execute CODEUNIT.RUN(CODEUNIT::"Upgrade New Version"). But the process is running only for the first company. The first question is, is it possible to run this process in turn? And how I can say nav to execute the codeunit in the next company? Maybe there is a better way to do this?
Many thanks in advance
0
Answers
I suppose you have choosen wrong way to upgrade.
I would offer you to upgrade 2009 to 2015 first and then, upgrade to 2018.
First step on 2009 Classic requires to click on each company. 2015 is already processing multiple companies on the fly.
Otherwice you spent on upgrade( prepare steps) more time, comparativelly if you ask for this work from experienced guys.
Reports transformation to RDLC
List -1h , Complex List -3h, Document -4h (dev hours)