Hi ,
We are using NAV 2016 and our costing method is weighted average cost.
I would like to have a solution for below scenario.
Item-A - Raw material - from Overseas Vednor
Item - B - Finished Product -Local Vendor
Item - C - Finished Product - Local Vendor
Importing raw material ( Item- A ) from an Overseas vendor and we pass that Item to the local supplier to make the final products (Item -B & Item -c).
Item-A received through purchase order and posted with proper actual landed cost.
We are receiving local supplier invoice to produce the item-B & Item-C from Raw material Item-A.
Currently, we are practicing Negative adjust to raw material item code and positive adjustment to finish products code with unit cost ( Raw material cost + Value added cost ).
what is the correct way to post the Finish products & Raw material consumption for above scenario with proper unit cost.
Thanks
MP
We are using NAV 2016 and our costing method is weighted average cost.
I would like to have a solution for below scenario.
Item-A - Raw material - from Overseas Vednor
Item - B - Finished Product -Local Vendor
Item - C - Finished Product - Local Vendor
Importing raw material ( Item- A ) from an Overseas vendor and we pass that Item to the local supplier to make the final products (Item -B & Item -c).
Item-A received through purchase order and posted with proper actual landed cost.
We are receiving local supplier invoice to produce the item-B & Item-C from Raw material Item-A.
Currently, we are practicing Negative adjust to raw material item code and positive adjustment to finish products code with unit cost ( Raw material cost + Value added cost ).
what is the correct way to post the Finish products & Raw material consumption for above scenario with proper unit cost.
Thanks
MP
0
Answers
-
Hi
One solution I would suggest is using Assembly Order.
1.Create Assembly order. Component is Item-A, Product is Item-B or Item-C.
2.Create a virtual location for local supplier.
3.Transfer Item-A from warehouse to local supplier.
4.Post Assembly Order
5.Transfer Item-B or Item-C from local supplier to warehouse.
6.Create Purchase Order(charge Item), allocate assemble cost to posted transfer receipt of Item-B or Item-C.
But, if you have case to send Item-B or Item-C directly from local supplier to your customer, you need to customize the Item charge allocation, to let system could allocate cost to Posted Assembly Order.1 -
Really appreciated for your time and valuable reply .
I will try above method and let you know.
We are not selling those items and it's for internal consumption purpose.
Thank you.
0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.6K Microsoft Dynamics NAV
- 18.7K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 320 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions