Hi everyone,
I have a problem when I try to do Revaluation item with costing method average, the program said "You cannot revalue individual item ledger entries for items that use the average costing method", it happen after I select the transaction in field Applies-to Entry. But there is no problem when I try with NAV 2017, please give me solution, thanks.
FYI, I using NAV 2013.
Answers
In 2017, if you calculate Per "Item Ledger Entry" for average cost item, you will also get error like "You must not revalue items with Costing Method Average, if Calculate Per is Item Ledger Entry."
I think we can revaluate average cost Item by Item ledger Entry is before 2013.