Hello,
we use the planning batch "Calculate Plan - Plan.Wksh. Batch Job" for planning in NAV2009R2 for a customer project.
Purchases, transfers and production orders are to be planned.
The components are set up with item tracking (lot no.)
The production takes place in location '01'.
The components are located in location '02' and must be transfered. Stockkeeping units with replenishment method "transfer" is set up for the component.
Two transfers are required for replenishing the production.
location: 02 -> 17 -> 01
As soon as a lot no. is entered in the item tracking of the components (no reservation!) of a released production order, too many planning lines are created when running the batch again.
transfer from 02 to 17 (2x)
transfer from 17 to 01 (4x)
All published hotfixes are installed. In NAV 2017, this issue is clearly solved.
Looking at the planning run and the reservation management codeunits I can not find the cause.
Has anyone ever had this problem?
thanks in advance