Your screenshot shows the work shift hours but that's not the work center calendar. You need to calculate the calendar for the work center using the Planning menu option toward the bottom of the work center card.
Also, make sure you select the appropriate capacity UOM I the drop down list when setting up work centers (100/hour, 100/batch etc)
If the calendar and UOM was not properly setup, there would be an error. Lets begin with what you expected the system to do? You replan and want what to happen?
Answers
MisConsultng
Also, make sure you select the appropriate capacity UOM I the drop down list when setting up work centers (100/hour, 100/batch etc)
Just on a sidenote, and I may be stupid, but shouldn't this be 08:00 - 18:00 then ?