Parallel scheduling of tools in production order
esbarrett
Member Posts: 5
Is anyone able to provide any guidance regarding how to parallel schedule tools in a production order so that they are considered in the planning process?
For example;
A specific mould is required for a manufacturing operation.
Only 1 mould exists for this specific operation; therefore if two separate production orders (each quantity 1) are required for this production item, then only one item can be produced at a time.
I have tried setting the mould up as a machine centre (also setup as a constrained resource) - and then parallel scheduling the mould machine centre alongside the person machine centre (also a constrained resource) - the intent being that each production item needs the person and the mould at the same time.
The problem I experienced with this setup is that the parallel operations on one of the two production orders scheduled the production person to start at one time and the mould to start at another time.
Any feedback is much appreciated.
For example;
A specific mould is required for a manufacturing operation.
Only 1 mould exists for this specific operation; therefore if two separate production orders (each quantity 1) are required for this production item, then only one item can be produced at a time.
I have tried setting the mould up as a machine centre (also setup as a constrained resource) - and then parallel scheduling the mould machine centre alongside the person machine centre (also a constrained resource) - the intent being that each production item needs the person and the mould at the same time.
The problem I experienced with this setup is that the parallel operations on one of the two production orders scheduled the production person to start at one time and the mould to start at another time.
Any feedback is much appreciated.
0
Comments
-
After much more testing I have concluded that parallel scheduling is probably best avoided.
No matter what I tried I couldn't get two identical work orders to start and finish at the same time - even though there were two capacities for every operation.
Back to serial routings and possible a customisation to handle the scheduling of tools.0
Categories
- All Categories
- 75 General
- 75 Announcements
- 66.7K Microsoft Dynamics NAV
- 18.8K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 610 NAV Courses, Exams & Certification
- 1.9K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 251 Dynamics CRM
- 103 Dynamics GP
- 6 Dynamics SL
- 1.5K Other
- 991 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 28 Design Patterns (General & Best Practices)
- Architectural Patterns
- 9 Design Patterns
- 4 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1K General Chat
- 1.6K Website
- 77 Testing
- 1.2K Download section
- 23 How Tos section
- 249 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions