MRP

midnight
Member Posts: 74
Just want to confirm that MRP looks at the "Due Date" of the production orders when we determine the time frame of the MRP run, and that this date can be changed to lengthen the time the production order is due to be completed (so not to be included in the MRP run).
Thanks
Thanks
0
Comments
-
MRP looks at the due date of the production order line to determine the supply of the item being produced and the due date of the components to determine the demand of the items being consumed.Olof Simren - Microsoft Dynamics NAV Expert | Founder of Naviona
My Dynamics NAV Blog: olofsimren.com
My Google Plus Profile
Naviona - My Dynamics NAV Partner0 -
Thank you.0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.6K Microsoft Dynamics NAV
- 18.7K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 320 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions