Hi guys I have specified case problem
I work in concrete ready mix company have more branches.
my purpose from company produce ready mix concrete.
every company have more batch plant
you input gravel and cement and water and sand to every batch planet as input and output or result ready mix concrete.
My question here what i must added in machine center and what must added in work center
Example
Company A
Batch pant 1 Batch plant 2
Workers input raw materials as Sand - Gravel -Cement-Water in batch plant to get ready mix
Supplier
car
Sand - Gravel -Cement-Water
input
Batch Plant 1----output
Ready mix
concrete
pump car
Customer
Customer sell ready mix
Ready mix concrete output is a,b,c,d this depend on components
Which here represent work center and which represent machine center
Thanks