Time calculation in work center- Dynamics NAV Manufacturing
Ashoka-NAV
Member Posts: 9
Hi All,
My client use NAV2009 R2 W1+ Manufacturing;
This is the scenario;
Work center B has assigned to production item A.
Work center B;
It is a oven.It can hold 1000 items at a time.Its holding time will vary item to item.
its 2 hours for item A.
now i have 3 production orders. each 120 of item A, 200 of Item A and 300 of item A regularly.
Whole quantity of item A(620) work center run time is 2 hours. (Qty 1 to 1000 its 2 hours).
how can i set the time in route card?
I need to set the time to calculate accurate time at the planning worksheet.
your comments are highly appreciate.:)
My client use NAV2009 R2 W1+ Manufacturing;
This is the scenario;
Work center B has assigned to production item A.
Work center B;
It is a oven.It can hold 1000 items at a time.Its holding time will vary item to item.
its 2 hours for item A.
now i have 3 production orders. each 120 of item A, 200 of Item A and 300 of item A regularly.
Whole quantity of item A(620) work center run time is 2 hours. (Qty 1 to 1000 its 2 hours).
how can i set the time in route card?
I need to set the time to calculate accurate time at the planning worksheet.
your comments are highly appreciate.:)
0
Categories
- All Categories
- 75 General
- 75 Announcements
- 66.7K Microsoft Dynamics NAV
- 18.8K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 610 NAV Courses, Exams & Certification
- 1.9K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 251 Dynamics CRM
- 103 Dynamics GP
- 6 Dynamics SL
- 1.5K Other
- 991 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 28 Design Patterns (General & Best Practices)
- Architectural Patterns
- 9 Design Patterns
- 4 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1K General Chat
- 1.6K Website
- 77 Testing
- 1.2K Download section
- 23 How Tos section
- 249 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions