Dynamics NAV 2013 Production schedule ?

Ashoka-NAVAshoka-NAV Member Posts: 9
edited 2013-06-13 in NAV Three Tier
Hi All,
Can anybody tell about production schedule in NAV 2013?
There is no default function to run production schedule(Gantt chart) like classic 2009. Is there any Add on to add production schedule to dynamics NAV 2013?

(It wasn't in 2009 RTC also)

Microsoft is saying that function is there in feature list;
default.html

Comments

  • ara3nara3n Member Posts: 9,256
    It's called Item Availability by Timeline in 2013 page 5530. They did release it fro NAV 2009 R2 but as separate objects and you have to implement the latest hotfix to compile the objects.
    Ahmed Rashed Amini
    Independent Consultant/Developer


    blog: https://dynamicsuser.net/nav/b/ara3n
  • flerollandflerolland Member Posts: 7
    Hi,

    There is an Add-on for Production Schedule : PlannerOne Production scheduler for NAV 2013 propose Gantt chart and much more...
    Please visit this site for more information : http://www.plannerone.com

    Best regards,
    François Le Rolland
    François Le Rolland
    R&D Team Leader
    Ortems - PlannerOne Production Scheduler for NAV
  • mkarlomkarlo Member Posts: 2
    Hi there,

    My company recently launched a visual production scheduling add-in for the role-tailored versions. It is completely integrated as page into Dynamics NAV. You can have a look here:
    http://www.netronic.com/vps

    Please let me know if you have any additional question, or need any kind of support. We are always happy to help.

    Regards,
    Martin