Load on Workcenter is not reduced until MO is finished

svenlindbacksvenlindback Member Posts: 3
The load is not reduced for the workcenter when an operation is reported.

Example:
I have a Manufacturing order, Qty = 10 PCE, for item "ZX" with two operations (Drilling and Painting).

I would expext that the load on the workcenter would be reduced when I report output for each operation. But I have to finish mark the MO before the load is removed from the workcenter for this MO ?

This means that I will have no capacity availble on the first operation until the MO is finished marked.

Comments

  • cernstcernst Member Posts: 280
    When you say report output do you also report time not just output quantity? In that case load should be reduced with the time reported.

    PS Welcome to mibuso :)
    _____________________
    NAV Freelance Consultant
  • svenlindbacksvenlindback Member Posts: 3
    I just post qty (it's an integration), but I will try to also add operation time