Dear All,
I have one issue in Planning worksheet. After running calculate regenerative plan, it shows only zero level production order planned and MRP of zero level in worksheet. It does not show production orders and MRP of more than one level which are their in same BOM. I have to run palnning worksheet again and again till all production order planning and their mrp appears in planning worksheet.
What could be the solution for it to get all MPS and MRP in one shot?
Rahane
0
Comments
Version 2009 Sp1.
I have Bicycle (1st level BOM) and Front Wheel, Back Wheel, etc. (2nd level BOM), and both the production orders are suggested by the Planning Worksheet.
Let me know what are setup involved into this process to verify with Cronus database.
Chn
Working in demo but not working in our Live database as there is no customisation done so far.
Thanks for your help.
PRR