Cost of goods sold was adjusted through the ajust Cost - Item entries batch job. the problem is that the original sales document had a posting date of 15/05/2012 and an adjustment entry was created by the system with the same document no. but with a later posting date of 28/06/12.
Pls what can be the cause of this?
0
Comments
If item which you are selling is production item, then one of its component reevaluated, so yours sold its also affected and its' COGS changed.
If it is purchased item then it is, revaluation of this item affected.
It could be also that you assigned freight charges. It's very easy to fin out how the Sales entry is applied against it. Find the inbound Item ledger entry and take a look.
Independent Consultant/Developer
blog: https://dynamicsuser.net/nav/b/ara3n
@Rashed.. the purchase invoice has a posting date earlier than the sales document
Thanks Guys
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book
If the item has been reevaluated so revaluation entry is there.
May i know what is your purpose behind revaluation ?