There is another post on the forum with this exact same discussion.
Do you have Cost Amount (Expected) on your Output Item Ledger Entry?
Is there an Invoiced Quantity on your Output Item Ledger Entry?
Is the production order have a status of Finished?
If your version is old enough the output will not invoice until the source of all of the consumption entries are fully invoiced regardless of the costing method.
Comments
You should turn on the debugger and see if there is any trigger in items table which changes the value of item's cost
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book
NAV Freelance Consultant
Do you have Cost Amount (Expected) on your Output Item Ledger Entry?
Is there an Invoiced Quantity on your Output Item Ledger Entry?
Is the production order have a status of Finished?
If your version is old enough the output will not invoice until the source of all of the consumption entries are fully invoiced regardless of the costing method.
KCP Consultores
You must change your status RPO to FPO, then you run Adjust Cost Item Entry, and check your cost...