When I create a new BOM version, how can I have the system go and update the affected production orders?
Is there a planning worksheet that will suggest an action message to refresh the production order or update the components?
The reason is because if the production order is released to the shop floor, the risk of you changing the components on the system when the component has already been actually used.
For all planned production orders, you will need to replan because it may affect the scheduling dates of the components involved with the new components.
OK. Thank you kind sir. This will save me time looking for such a thing.
I thought I might find it since the Prod. Order Line stores the BOM No. and Version, which should be quite helpful.
Answers
The reason is because if the production order is released to the shop floor, the risk of you changing the components on the system when the component has already been actually used.
For all planned production orders, you will need to replan because it may affect the scheduling dates of the components involved with the new components.
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book
I thought I might find it since the Prod. Order Line stores the BOM No. and Version, which should be quite helpful.