Hi All ,
Client is using the NAV 5.0 SP1. Client has 20K +items with FIFO costing method .
I know there are a bunch of posts out, there but what I want to do the process in a simple way so I wanted to get some feedback. I want to change the costing method from FIFO to AVERAGE of 20K + Items . Renaming and replacing items would be.... painful, so please explore your thoughts to change the costing method.
Thanks in Advance.
lally
0
Comments
there is iCMC from impuls, www.impuls-nbg.de. Best method I've seen so far.
with best regards
Jens
---
I am here: http://maps.google.com/maps?ll=52.553076,13.083742
I could not able to find any link in that site which was mentioned by you.
Please share change costing method link.
Thanks in advance
had to search with the full name... here it is:
https://www.impuls-solutions.com/Pages/1048.aspx
https://www.impuls-solutions.com/Docume ... N_2011.pdf
with best regards
Jens