hi all,
in the sandard Navision for a service item in a service order, there can be Active service order allocation entries with
one resource at a time.
I would like to ask if anyone implemented a way were we could allocated more than 1 resource at a time in a service item in a service order..... and how?!
any help is wellcome
thank you in advance for your help
Comments
How to manage multiple Resources on ONE Service Item
Any book or on-line help reference about this topic ?
TIA
Louis
unfortunately I didnt got any replies about this topic.
We did something custom which doesnt use the default navision module for allocation. Sorry I cannot help.
If you find any solution please post it.
Thank you,
WhiteLG
The only solution I have found is to re-enter, in the same service order, a new service line for the same service item with the same informations ... and it's then possible to assign another resource.
Somebody else has suggestions ?
Louis
It is used to validate the actual hours spent by the resources.
The issue is related to the planning, which precedes the activity :
Planning and Dispatching / Dispatch Board / Planning / Resource Allocation
Louis