Options

Calculate Standard cost

N11284N11284 Member Posts: 8
edited 2011-09-13 in NAV Three Tier
I can Calculate the Standard Cost of an item from the RTC but I am unable to find out how to Calculate the Standard Cost of all Items at once.
Is it possibe to do this?

I have over 400 products in stock and have just completed the Routings for each Item. I now want to calculate the Standard Cost of all 400 items. Must I do this one item at a time?

My Menu path after I Select the Item is

Related information>Item>Manufacturing>Calculate Cost.

This works fine if I select one item at a time but does not work if I try to select multiple items.

Any pointers or help appreciated.

Comments

  • Options
    N11284N11284 Member Posts: 8
    OK got it sorted, Found the Standard costs worksheet.
Sign In or Register to comment.