Error when calculating backward calender

hardik_shah
Member Posts: 219
Dear Experts!!!
Need Help...
when m trying to create production order it Reflects error "Error when calculating backward
calender is not available before 04.04.11 for work center 003"
Need Help...
when m trying to create production order it Reflects error "Error when calculating backward
calender is not available before 04.04.11 for work center 003"
0
Comments
-
Something is wrong in the routing or on the work center maybe wrong unit of measure.
Easiest way to find out should be to create a calendar in the past._____________________
NAV Freelance Consultant0 -
Dear cernst,
Thx for your valuable help...
cernst if possible please let me know that from where i can create calender in the
past ? ? ?0 -
When you calculate calendars for work center you can change the dates under the option tab. that way you can set dates in the past._____________________
NAV Freelance Consultant0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.6K Microsoft Dynamics NAV
- 18.7K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 320 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions