Adjust cost Item entries taking too loooong in NAV 2009sp1

sendohsendoh Member Posts: 207
Hi Guys,

we have 3 months transactions in mfg,sales,purchase and GL then we run ACIE for the first time, it takes 8 days I know it can this happen because we run this batch job for the first time but when we run it again after 1 week, its 3 days now and it still not finish, I expect to finish this just an hours because back log transation is already adjusted, pleased advise what would be the possible reason of this.btw, we're using NAV 2009sp1 and MSSQLServer2008. [-o<

Regards,

Sendoh
Sendoh
be smart before being a clever.

Comments

  • ara3nara3n Member Posts: 9,256
    Are you running calc low level code?

    This way NAV adjusts raw material first. Then 1st level bom and then second level etc.
    Ahmed Rashed Amini
    Independent Consultant/Developer


    blog: https://dynamicsuser.net/nav/b/ara3n
  • sendohsendoh Member Posts: 207
    Hi Ara3n,

    Thanks for the reply, we don't run that yet, but we'll try that suggestion, btw forgot to mention our costing method is average.

    regards,
    Sendoh