Hi ,
I have a question regarding the planning functionality.
I created an absence for a work center using the registered absence facility.
This absence is even reflected in the shop calendar for that work center.
But for some reason , when i run planning and carry out the suggested action messages, the work center load reflects that
the firm planned order will run during the time period during which the absence was registered earlier as well.
Why does this happen?
Ideally nothing should be allocated to that time slot of the work center when the work center is down right?