I've runthe batch job to updated cost of all production orders (Released & Finished).
The cost of released production order updated successfully BUT it's not updaintg the Cost for Finished Prod. Order.

please help.

Jai Verma
Regards,
Jai Verma

Comments

  • chengalasettyvsraochengalasettyvsrao Member Posts: 711
    Did you post the invoice for the rawmaterial which you consumed ?

    Did you change the status of that Production order to Finished ?

    Did you run the Adjust cost Item entreis batch job ?
  • manishgoyalmanishgoyal Member Posts: 52
    for update costing status should be finished that you have to run batch job Adjust cost-Item entries.
    Manish Goyal
  • jaiverma2k2jaiverma2k2 Member Posts: 112
    Thanks a lot chengal, probelm is solve now.