Hi,
I am facing a problem while running the planning worksheet,
I have defined a work center as being capacity constrained at 100% because I don't want the machine centers working on an order unless it has completed all the operations related to an earlier order(This is a food manufacturing process)
Now when I am running the planning worksheet. The planning algorithm,for some reason, only takes one particular shift from the two shifts that are defined in the shop calendar.
For eg
12:00:00 pm - 11:59:59 pm Shift 1
12:00:00 am - 11:59:59 am Shift 2
After planning is done and the orders are released to production , every order is run by only one shift (Shift 1)
Is there a setting that needs to be done so that planning takes into account both the shifts.
Am i doing something incorrect?
Please advise
0
Comments
MVP - Dynamics NAV
My BLOG
NAVERTICA a.s.
Monday - S1 - 12:00:00 am - 11:59:59 AM
Monday - S2 - 12:00:00 pm - 11:59:59 PM
Tuesday - S1 - 12:00:00 am - 11:59:59 AM
Tuesday - S2 - 12:00:00 pm - 11:59:59 PM
Wednesday - S1 - 12:00:00 am - 11:59:59 AM
Wednesday - S2 - 12:00:00 pm - 11:59:59 PM
Thursday - S1 - 12:00:00 am - 11:59:59 AM
Thursday - S2 - 12:00:00 pm - 11:59:59 PM
Friday - S1 - 12:00:00 am - 11:59:59 AM
Friday - S2 - 12:00:00 pm - 11:59:59 PM
Saturday - S1 - 12:00:00 am - 11:59:59 AM
Saturday - S2 - 12:00:00 pm - 11:59:59 PM
Sunday - S1 - 12:00:00 am - 11:59:59 AM
Sunday - S2 - 12:00:00 pm - 11:59:59 PM