Hi all,

We have encountered a problem with certain items when running MPS/MRP and have not be able to identify the reason. The error messages received in the planning log says "The date is not valid" .

Does anybody know what triggers this problem, what the issue is and how to resolve it?

NAV version is 5 SP1 and database server is MS SQL 2005.

Comments

  • cernstcernst Member Posts: 280
    Hi,

    I've hade this problem before, the problem then was that there where no date on a sales order line. So check all demand lines purch.order, pcomponents etc to see if you have a blank date somewhere.
    _____________________
    NAV Freelance Consultant
  • AirisLTAirisLT Member Posts: 3
    I checked the sales and purchase lines. I also checked the production orders components lines . All dates are provided. Who else can influence the occurrence of this error?
  • gvolkovgvolkov Member Posts: 196
    Why not turn on the debugger and see whats missing?
    Microsoft Certified Technology Specialist
    Microsoft Certified Business Management Solutions Professional
    Microsoft Certified Business Management Solutions Specialist

    http://www.navisiontech.com
Sign In or Register to comment.