order date in planning worksheet

vijay_gvijay_g Member Posts: 884
hi,
can someone describe me about order date and end date in planing regenerative plan?
when i am filling forecasting quantity for two date it does not combining total quanity.

date qty
25/08/10 100
26/08/10 100

it is giving me only 100 quanity in planning worksheet
order date --- 25/08/10
end date ---- 26/08/10



any help would be arrpritiated

Comments

  • kapil4dynamicskapil4dynamics Member Posts: 591
    From F1

    Order Date: If the field is filled in, the Due Date field will be calculated from this date

    Ending Date: This field contains the ending date of the manufacturing process if the planned supply is a production order. AND

    This field contains the ending date of the shipping time if the planned supply is a transfer order.
    Kapil Khanna