hi,
can someone describe me about order date and end date in planing regenerative plan?
when i am filling forecasting quantity for two date it does not combining total quanity.
date qty
25/08/10 100
26/08/10 100
it is giving me only 100 quanity in planning worksheet
order date --- 25/08/10
end date ---- 26/08/10
any help would be arrpritiated
0
Comments
Order Date: If the field is filled in, the Due Date field will be calculated from this date
Ending Date: This field contains the ending date of the manufacturing process if the planned supply is a production order. AND