The machine center and work center is used in the routings. That's where the cost is being allocated.
I was answering your question on whether there's a direct link on how the cost is allocated. The answer is no. However, if you sum up the cost the raw materials and the routing costs, the total will be equal to the cost on the output.
Comments
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book
I think,
The total cost = Cost of Raw Material(Production BOM) +
Cost of processing the Raw Material (Routing).
What then is the use of the Direct unit cost in the Machine center card?
Thanks
I was answering your question on whether there's a direct link on how the cost is allocated. The answer is no. However, if you sum up the cost the raw materials and the routing costs, the total will be equal to the cost on the output.
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book