Ajust Average Cost on Purchase receipt

Etienne11
Member Posts: 3
Hi,
I have a question for you.
I use Dynamics NAV 5.0 and all my item setup on average cost.
If I want to do a revaluation journal for an item but there is a purchase receipt not invoiced, Navision doesn't take all receip not invoicing for update average cost.
In some cases, reception can take many weeks before invoice, which make many problems because we can not reevaluate the inventory.
I wanted to know the impact that this may, if i remove the validation for receiption not invoiced
I did some tests and all seems to work good
I would like to be on your opignon
Thank you
I have a question for you.
I use Dynamics NAV 5.0 and all my item setup on average cost.
If I want to do a revaluation journal for an item but there is a purchase receipt not invoiced, Navision doesn't take all receip not invoicing for update average cost.
In some cases, reception can take many weeks before invoice, which make many problems because we can not reevaluate the inventory.
I wanted to know the impact that this may, if i remove the validation for receiption not invoiced
I did some tests and all seems to work good
I would like to be on your opignon
Thank you
0
Comments
-
In some cases, reception can take many weeks before invoice,
The revaluation of items is described in detail in the online help of NAV. I suggest that you read it carefully and discuss the process and the consequences with your financials/bookkeeping department.0 -
rhpnt wrote:The revaluation of items is described in detail in the online help of NAV. I suggest that you read it carefully and discuss the process and the consequences with your financials/bookkeeping department.
Also I'm diggin this video about revaluation journals
http://msdn.microsoft.com/en-us/dynamic ... 25261.aspx
Talks about the differences & what you can & cannot do depending on your cost type0 -
Why do you want to revaluate an entry that still doesn't have a final cost?
Once the invoice is posted, that entry will be finally valuated and your previous revaluation (if you get to do that) will be useless...0 -
Hi crisnicolas,
I want to revaluate an item before have a final cost
because on my indirect cost, I have some factor and if this % of indirect cost not good
(some time upper because i can have some reserve on my indect cost) i need to revaluate my average cost
This is why some time i need to revaluate stock before I invoice0 -
FYI, The cost of the items will be valued back to the actual cost when the invoice is recevied.
This is a common request for companies that have razor thin margins and need to know the cost of the item for a shipment coming in so they can make a proper quote for the customers. However, we don't recommend using revaluation journals for this purpose since it creates too many entries.
We create a screen to take the proforma invoice and estimate the total freight in costs so the salespeople can get an approximate to quote their customers.Confessions of a Dynamics NAV Consultant = my blog
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book0 -
FYI, The cost of the items will be valued back to the actual cost when the invoice is recevied.
This is a common request for companies that have razor thin margins and need to know the cost of the item for a shipment coming in so they can make a proper quote for the customers. However, we don't recommend using revaluation journals for this purpose since it creates too many entries.
We create a screen to take the proforma invoice and estimate the total freight in costs so the salespeople can get a more accurate approximate to quote their customers.Confessions of a Dynamics NAV Consultant = my blog
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book0 -
Etienne11 wrote:Hi crisnicolas,
I want to revaluate an item before have a final cost
because on my indirect cost, I have some factor and if this % of indirect cost not good
(some time upper because i can have some reserve on my indect cost) i need to revaluate my average cost
This is why some time i need to revaluate stock before I invoiceRegards,
Andwian0 -
Because the additional costs for the receipt isn't known yet since you don't have the invoices from the shipping vendors.Confessions of a Dynamics NAV Consultant = my blog
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.6K Microsoft Dynamics NAV
- 18.7K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 320 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions