Hi
I have problem with planning my production.
There are 2 Items A and B.
Item A have a BOM where is line with item B and Quantity per Unit 2 pcs.
Items setup:
Replenishment System: Production Order
Manufacturing Policy: Make-To-Order
Reordering Policy: Lof-for-Lot
Include Inventory: TRUE
Reservation: Optional
Item's Inevtory:
A=2
B=3
Now I have Sales Order for 10pcs of A item.
I run Calculate Regenerative Plan in Planning Worksheet only for MPS and system gives me line with 8pcs of A Item, which is correct.
But when I run MRP system create line for 16pcs of B item. Why B's Inventory is not included in this calculation?
Is there a method to have multi-level Prodcution Orders and plann all it lines?
0
Comments
Manufacturing Policy: Make-To-Stock