Infinite Loading

b2amolb2amol Member Posts: 64
Hi,

Using NAV2009; I am using work centers in routing. While i run Calculate Planning Worksheet - Net change Plan or Regenerative Plan, I get error 'Error Calculating backward - Calender is not avaliable before....'

My goal is to assign infinite capacity to the work center (its a sub-contracter); and avoid creating Capacity Calendar for it. How it can be achieved?

Thanks,

Amol