Needed Quantity in Order Planning

podollypodolly Member Posts: 84
Hi all,

I am generating the order planning on released production order. 1 of the components (say item A) is replenished with production order, which required 0.7KG of a metal (say item B). After I calculate the plan, it shows a released prod. order for item A and a purchase order for item B. What I don't understand is, why the needed quantity and Qty. to order for item B go to 1 instead of 0.7 on the order planning window?

I have set up on item card B, base unit of measure = KG, where qty. per unit of measure = 1.
On the Prod BOM line of A, it requires Quantity = 0.7, Quantity per = 0.7
Is there anything wrong with the setup?

Answers

  • FecaFeca Member Posts: 5
    Hi,

    What is the number in "Rounding Precision" field on Items form, Replenishment tab?
    (View this field's help, how it's work.)
  • podollypodolly Member Posts: 84
    Oh, got it! Really forget about this. Thanks, Feca :D
Sign In or Register to comment.