order promise issue

kjzda
Member Posts: 4
there are three item : one is FG , two is SFG ,three is RM ;BOM structure is FG<<--SFG<<--RM; the manufacture policy of FG is 'make to order ' , reorder policy is 'order ;SFG and RM is 'make to stock' ,reorder policy is 'lot for lot';the production cycle and purchase cycle only need oned day .SFG and FG have no stock ,RM have enough stock.
now(work date is 2009-09-16) I create a firm planned production order for SFG,its due date is '2009-09-23' ,and i create a sale order for FG ,the 'planning shipment date ' is '2009-09-18' ,when i run 'order promise-->>capabale to promise ', system give me suggestion earliest shipment date is '2009-09- 18' ,and in planning worksheet , system suggestion create a new production order for SFG in '2009-09-17' .
my question : because i have anrranged to produce SFG in '2009-09-23' , so system should consider that firm planned production ordr by manual. and when run order promise ,should suggest earliest shipment date is '2009-09- 23' ,not is '2009-09- 18' .
can anyone tell me how to get that result .or if should i do more setup parameters in system ?
now(work date is 2009-09-16) I create a firm planned production order for SFG,its due date is '2009-09-23' ,and i create a sale order for FG ,the 'planning shipment date ' is '2009-09-18' ,when i run 'order promise-->>capabale to promise ', system give me suggestion earliest shipment date is '2009-09- 18' ,and in planning worksheet , system suggestion create a new production order for SFG in '2009-09-17' .
my question : because i have anrranged to produce SFG in '2009-09-23' , so system should consider that firm planned production ordr by manual. and when run order promise ,should suggest earliest shipment date is '2009-09- 23' ,not is '2009-09- 18' .
can anyone tell me how to get that result .or if should i do more setup parameters in system ?
0
Comments
-
kjzda wrote:there are three item : one is FG , two is SFG ,three is RM ;BOM structure is FG<<--SFG<<--RM; the manufacture policy of FG is 'make to order ' , reorder policy is 'order ;SFG and RM is 'make to stock' ,reorder policy is 'lot for lot';the production cycle and purchase cycle only need oned day .SFG and FG have no stock ,RM have enough stock.
now(work date is 2009-09-16) I create a firm planned production order for SFG,its due date is '2009-09-23' ,and i create a sale order for FG ,the 'planning shipment date ' is '2009-09-18' ,when i run 'order promise-->>capabale to promise ', system give me suggestion earliest shipment date is '2009-09- 18' ,and in planning worksheet , system suggestion create a new production order for SFG in '2009-09-17' .
my question : because i have anrranged to produce SFG in '2009-09-23' , so system should consider that firm planned production ordr by manual. and when run order promise ,should suggest earliest shipment date is '2009-09- 23' ,not is '2009-09- 18' .
can anyone tell me how to get that result .or if should i do more setup parameters in system ?
Order promising as the name suggests will work for order only. If u have inventory on hand then only it is considered in dates else as per your scenario how system will come to know that ur Production order for SFG is meant for to be consumed in FG. There shud be some established relationship b/w ur production order for SFG and sales order for FG for including in account when calculating the dates.Kapil Khanna0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.6K Microsoft Dynamics NAV
- 18.7K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 320 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions