Increase of Work centre capacity for a particular day

Jaideep_GhoshJaideep_Ghosh Member Posts: 50
Hi,
Can I increase the Capacity of a Work centre for a Particular Day ? Suppose a Work Centre's capacity is 8 hrs daily.
To carry out an urgent sales order the work centre has been asked to work overtime in one particular day. On that particular day it's capacity needs to be increased to say 20 hrs.
How we can do this ?

Answers

  • SumitSumit Member Posts: 58
    Try with modifying 'Calendar entries' for the work center for that day.
    i.e. start time & End time. <Refresh>
    My friend is "Search the Forum"
  • Jaideep_GhoshJaideep_Ghosh Member Posts: 50
    Thanks, But where can I find "Calender Entries" in a Work Centre ? I am going to Worck Center>Planning >Calender. But after that how can I define hours for a particular day?
  • SumitSumit Member Posts: 58
    In RTC.
    Worck Center>Planning >Calender
    Click on "Show Matrix".
    This take you to Work Center calendar Matrix screen.
    Double Click on the W/C value of the day.
    This take you to Edit calendar entries screen.
    Change the time.

    In Classic,
    Select the value, click on dn arrow.
    This take you to Edit calendar entries screen.
    Change the time.
    My friend is "Search the Forum"
  • Jaideep_GhoshJaideep_Ghosh Member Posts: 50
    Thank you very much !!!
  • SumitSumit Member Posts: 58
    You're welcome !
    My friend is "Search the Forum"