manozmanoz Member Posts: 26
A production unit is having two machines. One is Mixer and the other one is Extruder. Suppose, 1000 KG of Finished Good is to be produced. The Required quantity of raw material is divided into N batches. So 1 batch contains 1000/N KG of Raw Materials, in proportion according to the Production BOM. initially first batch is fed to the Mixer. After this batch of mixed material is coming out of Mixer,It is fed to the Extruder. By this time, 2nd batch is fed to the Mixer.So here onwards, the operation is parallel.


So in short, the steps of processing batches are follows.

Mixer Extruder

Batch1 No processing
Batch2 Batch1
Batch3 Batch2
Batch4 Batch3
...... ......
..... ......
Batch N Batch(N-1)
No processing Batch N


So from step 2 to step n-1, the operation is parallel.


Suppose its taking 1 minute as runtime and 1 minute as setup time per KG.

How will we setup a routing for this procedure in navision?

:roll:
(nav 5.0)

Thanks.

Comments

  • kapil4dynamicskapil4dynamics Member Posts: 591
    viewtopic.php?f=23&t=35991&hilit=routing

    see this might help you.
    Kapil Khanna
  • manozmanoz Member Posts: 26
    Thanks

    But the issue here is how to setup for this particualr scenario. we cannot say its completely paralleel operation.

    For the first batch and last batch of RM, its serial, as described in first post.

    So Starting Date and Ending Date of Production Should be correct.

    Anybody had setup routing for this scenario?
  • SumitSumit Member Posts: 58
    Please try your scenario with "Send-Ahead Quantity" field.
    You could define a batch size for your Mixer unit.
    This might be helpful.
    My friend is "Search the Forum"
  • manozmanoz Member Posts: 26
    Sumit.....

    Your solution works fine !
    :D

    Thanks a lot....



    (Sorry for the delay......)
  • SumitSumit Member Posts: 58
    You are welcome.
    My friend is "Search the Forum"