How can I set parallel Routing in Navision5.0Sp1?

siryutsiryut Member Posts: 5
Hi Expert,

Could you please tell me about how can I set parallel Routing in Navision5.0Sp1?

I set Next Operation = 10|20 but after certified Routing the system refresh value to 10.

Comments

  • kapil4dynamicskapil4dynamics Member Posts: 591
    U haven't mentioned complete activity of urs, if u do not have 10 or 20 in operation number, and have a number smaller than these then it will be parallel. Have u done so ? <Edit> And yes do not forget to mention in type as parallel. :mrgreen:
    Kapil Khanna
  • DaveTDaveT Member Posts: 1,039
    Hi,
    Try have you tried to set the Type in the header to parallel. Also when setting up it's easier to blank the previous operations and let the certification do it for you. Here's an example
    Op No.    Next Op No.  Previous Op No.     Type	                No.	
    10          20|30                                    Work Center       100	
    20          40               10                      Machine Center   410	
    30          40               10                      Machine Center   420	
    40          50               20|30                 Machine Center   440	
    50                            40                      Machine Center   110
    
    Dave Treanor