Hi,
I need a clarification on the following: On the Inventory setup window, Automatic Cost Posting is checked and Automatic Cost Adjustment is set to Always.
If both of the above options are checked, is it necessary to run the Adjust Cost Item Entries batch job and Post Inventory Cost to G/L?
Thanks and Regards,
Bea.
0
Comments
So yes, even if just once a month.
I remember a presentor mentioned this in one of the NAV sessions back when 5.0 was released.
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book
I would uncheck the settings and run them as batch jobs overnight for performance reasons.
Independent Consultant/Developer
blog: https://dynamicsuser.net/nav/b/ara3n
Hello all,
Why? Why should we run the adjust cost item entries job even though the automatic cost adjustment set to always?
Dynamics NAV Developer since 2005
You need to adjust it after inventory has been purchased.
Sr. Project Manager
S-Metric, LLC
jsung@smetric.com
I have a question regarding automatic cost adjustments. We are not using the automatic feature, so I have to run the procedure at the end of every day, is there a way of automate this to take place over night let's say?
Thank you
Maria
A little tweaking to hide the dialog is required on the process though.
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book
Dynamics West
http://www.dynamicswest.com
Independent Consultant/Developer
blog: https://dynamicsuser.net/nav/b/ara3n
I am NOT concerned about understanding what Adjust Costs does. I have written processes that completely handle errors caused by older versions of Navision. I know what all the tables do and how to correct them. Once this is done we can turn Automatic Cost Posting even if the Item Ledger goes back to 1995.
I AM concerned about what AUTOMATIC Cost Adjustment does. It does NOT seem to include posting Item entries through the Job Journal. So it looks like you have to run the MANUAL Adjust Costs no matter what else you do. What I would like to know is just what does Automatic Cost Adjustments do or not do, because it does NOT seem to replace the Adjust Costs process.
Dynamics West
http://www.dynamicswest.com
https://connect.microsoft.com/dynamicssuggestions
Independent Consultant/Developer
blog: https://dynamicsuser.net/nav/b/ara3n
Yes, you have to run adjust cost process no matter what.
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book
Dynamics West
http://www.dynamicswest.com
You have to ask the higher beings (MSFT), grasshopper.
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book
Dynamics West
http://www.dynamicswest.com
Henrik Helgesen,
President | Helgesen Consulting
about.me | LinkedIN
Independent Consultant/Developer
blog: https://dynamicsuser.net/nav/b/ara3n