Hi,
I have several orders where consumptions have been posted already but no output were posted. So we need to cancel those orders and we dont know the right way to do that. There are thousands of work orders like that so my client does not want to go order by order to make all adjustments.
Does anyone has an idea on how we can modify the system to get rid off those orders??
Thanks
0
Answers
The question you posed is too big to answer on this forum.
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book
You need to post the output and reverse the it through item journal
Independent Consultant/Developer
blog: https://dynamicsuser.net/nav/b/ara3n
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book
Thanks
NAV Freelance Consultant
Once you've started a production order and posted any entries, you have to go through the process and follow the steps mentioned above.
Independent Consultant/Developer
blog: https://dynamicsuser.net/nav/b/ara3n
1. Why are there so many unfinished WO?
2. What are the reasons for no output?
3. What about WIP? Comfortable recognizing them as cost?
4. Why is the WO created in the first place?
These are some of the questions I would ASK the client first before recommending they just finish the WO.
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book
All those questions have already been asked and responded by the client. There was an error made by the person who was in charge of the production. Now they have another person who understands well how the process should work.
Right now , i know that the way to correct that is by doing some adjustments but i was just asking if someone has another way to correct that.
thanks
Alex makes some valuable points, and I believe you miss his point, you have the answer, it was a processing issue, but moving forward you need to report output, now you state teh inventory is now correct, but is the consumption? Does the cost involve routing issues? I ask as if you are anything but standard this is going to affect your costing and you will need to correct all of this, if not it goes to variance and accounts need to know how to handle this as you have clearly mis-stated COGs in the past depending upon your WIP account posting.
Sorry but put simply, book the items in on an output journal, finish the order, run teh adjust cost item entries, remove the stock, post a revaluation journal wherever you feel necessary. These are the consequences of the original users actions, you need to unpick it all to get on a firm footing to move forward - there is no quick fix in my opinion to this and you should tell your client this.
I understand all your points. So the only way is the way that you mentionned . That's fine.
Thanks all for your ideas.