Hi,
I'm using the 'Calculate Plan' feature in the Requisition Worksheet. Can anybody explain in layman's terms exactly how each parameter in the request form affects the batch job - the help is pretty basic on this. I'm after how the transactions (SO, PO, Stock, Forecast Entries etc) are filtered by the parameters - 'Start Date', 'End Date', 'Exclude Forecast Before'.
Any help appreciated,
Jonathan
0
Comments
Ending Date - this is where the planning stops. If you set this to be 30/05/2009 it will ignore any requirements after this date.
Exclude Forecast Before - if you attach a forecast then the system will build to the forecast as a form of demand. If you had an unfulfilled forecast in March you would not want the system to plan to make for it, if you did not use the exclude it would do this. Depending upon your forecast planning this would either be set to today, or the start of the month, although I would not personally be planning to biuld/buy to a monthly forecast towards the end of the month.