Work center costs
ajmalsherif
Member Posts: 111
Hi and thanks for reading this...
I have an Item with a Production BOM No. The Item also has a Routing No which goes off to the Routing card and Work centers. I have added costs on the Work Ctr card (Posting tab) for Indirect Cost % and Overhead Rate.
In History<Finished Prod Orders - these costs are not coming through on the Capacity LE (though the Item VE are ok). Neither is anything showing in Prod Order Stats. for Capacity Stock/Overhead. However, the Detailed Calculation report is showing the correct sum of the cost for the work center =D> (ie Total cost which is Indirect Cost % PLUS Overhead Rate).
On another issue i cant seem to move Prod Orders (the red diamond) on the Production Schedule - Production Order View. When i try the save option first i get a message saying 'Overflow under type conversion of Code to Code PO_Firm000009' it then also says
'Error creating conflict result XML)
Thanks
I have an Item with a Production BOM No. The Item also has a Routing No which goes off to the Routing card and Work centers. I have added costs on the Work Ctr card (Posting tab) for Indirect Cost % and Overhead Rate.
In History<Finished Prod Orders - these costs are not coming through on the Capacity LE (though the Item VE are ok). Neither is anything showing in Prod Order Stats. for Capacity Stock/Overhead. However, the Detailed Calculation report is showing the correct sum of the cost for the work center =D> (ie Total cost which is Indirect Cost % PLUS Overhead Rate).
On another issue i cant seem to move Prod Orders (the red diamond) on the Production Schedule - Production Order View. When i try the save option first i get a message saying 'Overflow under type conversion of Code to Code PO_Firm000009' it then also says
'Error creating conflict result XML)
Thanks
0
Comments
-
Did you run report 795 "Adjust Cost - Item Entries" ?ajmalsherif wrote:... these costs are not coming through on the Capacity LE (though the Item VE are ok). Neither is anything showing in Prod Order Stats. for Capacity Stock/Overhead.Kai Kowalewski0 -
Reasons :
I. If u have mentioned unit cost calculation on ur work center as time and haven't specified time on routing lines. See ur starting date and time and ending date /time they will be equal. They shudnt be equal to have calc as per time. And if u have only setup time make sure that u have checked "Cost. incl. setup" in mfg setup.
II. Make sure u have not selected specified unit cost on work center if u have then make sure u have these costs mentioned on routing lines because if u select the costs on work centers wont be considered.
But as u have mentioned u have only indirect costs % and overhead rate then I is 90% sure.Kapil Khanna0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.7K Microsoft Dynamics NAV
- 18.8K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 333 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions