Running Planning Worksheet in manufacturing

ajmalsherifajmalsherif Member Posts: 111
Hi learned friends

I am trying to run the Planning worksheet but i am getting the following message:

There is no planning routing line within the filter.
Filters: Worksheet template Name: PLANNING, Worksheet Batch Name: DEFAULT, Worksheet Line No 10000 Routing

I am using manufacturing for the first time on a test company and have created a BOM. I was hoping the worksheet would tell me my shortfall

Comments

  • AdamRoueAdamRoue Member Posts: 1,283
    Check the BOM for an operation link code, and verify that the attached routing is correct.

    Check the work centres on the routes have calendars into the future.

    If you are looking to test in a test company I would suggest you create your won new item with BOM and route on a blank company to ensure existing data is not your issue.
    The art of teaching is clarity and the art of learning is to listen
  • ajmalsherifajmalsherif Member Posts: 111
    Hi Adam

    thanks for the suggestion - it was the calendars that needed setting up for the work centers (calendar<calculate)

    On another but related issue i am running the Req Worksheet but it is repeating some item numbers for ex Item no GH222 is repeated - details are the same. It may be as i forgot i had to set up sku's so went back for some items :?:

    regards

    Ajmal