hi all
im new to this production order
i have created a production BOM & routing and attached the same to Item card in replnishement.
when i try to create a planned prod order in functions i'm trying to refreshing a backward & the error popups says "error when calculating backward. calendar is not available before (date) for work centre "no" .
can anyone help me on this...
im using the flushing method as manual in replnishment tab as well as in work centre card.
thanks
0
Comments
It looks like you do not have the work centre capacity calander setup up for the work center specified. Go to the work centre card and under the Planning Button select the Calander option. Then use Functions Calculate/Recalculate to set this up.
Dynamics Nav Add-ons
http://www.simplydynamics.ie/Addons.html
i had that setup, but i didn't know how to run the calculate. now its working fine
thanks for your help
Dynamics Nav Add-ons
http://www.simplydynamics.ie/Addons.html