The code that defaults it is in Sales header. Have you modified it?
IF "Document Type" IN ["Document Type"::Order,"Document Type"::Invoice,"Document Type"::Quote] THEN
BEGIN
"Shipment Date" := WORKDATE;
"Order Date" := WORKDATE;
END;
Ahmed Rashed Amini
Independent Consultant/Developer
When Ever I do integrations, I always load the data into a new 50000 table, and then create orders. This way the user can fix any data that they are required and don't need to mess with the xmlfile.
Ahmed Rashed Amini
Independent Consultant/Developer
When Ever I do integrations, I always load the data into a new 50000 table, and then create orders. This way the user can fix any data that they are required and don't need to mess with the xmlfile
Yes its a good idea but its my first implementation and I have not got much time to change the flow.
its just the work date on chronus is ahead the system date. I hope it will not cause a major issue in deployment.
You are importing it from the xml file. So what is the date in xml file?
You need to pay attention to sequence of triggers. OnInsert Trigger is run last so it will run the code I mentioned. Turn on the debugger and put some breakpoint on insert trigger.
Ahmed Rashed Amini
Independent Consultant/Developer
Answers
The code that defaults it is in Sales header. Have you modified it?
Independent Consultant/Developer
blog: https://dynamicsuser.net/nav/b/ara3n
Also search for "Shipment Date" in header.
Also how does your xmlport look like?
When Ever I do integrations, I always load the data into a new 50000 table, and then create orders. This way the user can fix any data that they are required and don't need to mess with the xmlfile.
Independent Consultant/Developer
blog: https://dynamicsuser.net/nav/b/ara3n
Yes
Also search for "Shipment Date" in header.
I did it comes up as system date
Also how does your xmlport look like?
When Ever I do integrations, I always load the data into a new 50000 table, and then create orders. This way the user can fix any data that they are required and don't need to mess with the xmlfile
Yes its a good idea but its my first implementation and I have not got much time to change the flow.
its just the work date on chronus is ahead the system date. I hope it will not cause a major issue in deployment.
You need to pay attention to sequence of triggers. OnInsert Trigger is run last so it will run the code I mentioned. Turn on the debugger and put some breakpoint on insert trigger.
Independent Consultant/Developer
blog: https://dynamicsuser.net/nav/b/ara3n
its work date in xml file.
ill try to debug on insert triggers and see how it goes.
regards